Decommissioning during the Access Building to Controlled Area project at Cofrentes Nuclear Power Plant
Spain
Iberdrola hired IDOM for the execution of the turnkey project of the new building in order to access to the controlled area in the Cofrentes NPP. Firstly, it was necessary the the old dining room building and locker room demolition as well as the relocation of the dosimetry (Quicky) service, of which IDOM acted as Construction Works Manager. Continuous coordination with de Radiological Protection department was necessary during the removal of material from the excavation.