Senegal
The TIER III Data Centre, which has the capacity to be expanded to TIER IV, was developed with the challenges of constructing this type of building in Senegal in mind. A careful analysis of the construction items and LLI was carried out to ensure correct execution of the construction while meeting the delivery deadlines.
IT capacity: 1.8 MW
IDOM was responsible for the entire project, including the “Basic Project” and “Executive Project” design phases. The elements included were:
- Architecture
- Civil engineering
- Structure
- Electrical
- IT, CCTV, Access Control
- Fire protection and fire alarm
- Air conditioning (HVAC)
- BMS and PMS